I found a schedule that details all the planned stages from drywall to move-in.  Here it is:

September 2006
9/6 – Wall texturing
9/7 – Post-drywall clean-up
9/8 – Primer painting and Exterior Paint.  Trim and Cabinet delivery.
9/9 – Vinyl and Tile installation
9/11 & 12 – Install Trim and Cabinets
9/13 & 14 – Interior paint
9/15 – Install countertops and measure mirrors.  Deliver light pack and install water meter.
9/16 – Electric Trim
9/18 – Plumbing Trim
9/19 – HVAC Trim and Install Mirrors
9/20 – Drywall final detailing, Fireplace light-up check and Attic Insulation.
9/21 – Carpet sweep, Windows, Shelving and 1/4 Round.
9/22 – Final paint touch-up
9/23 - Install Carpet
9/25 – Install door hardware
9/26 – Window cleaning and screen installation.  Appliance installation.
9/27 – “Punch Days” and C.O (?)
9/28 – “Punch Days” and I.L.C and D.C. (?)
9/29 – Walk-through drywall final inspection
9/30 – Walk-through paint final inspection

October 2006
10/9 – Construction Team final quality walk-through
10/13 – KB Home & HOA Management final quality walk-through
10/16 – Home Owner orientation walk-through
10/18 – Complete any final drywall corrections
10/19 – Complete any final paint corrections
10/23 – Closing!!!

Note:  Final closing was not complete until 10/30 to allow for completion of a few minor touch-ups.